The Corridors 8 & 10d Motorway Project in North Macedonia continues to make steady progress under the execution of the ENKA-Bechtel Joint Venture. More than 1,500 personnel, including subcontractors, are currently working across various project areas.
In sections 1, 2 and 4, earthworks and structural construction are progressing alongside ongoing drainage works. As of the end of August 2026, a total of 7.2 million m³ of excavation, 2.6 million m³ of fill, 1.7 million tonnes of aggregate production and 130,000 m³ of concrete works have been completed.
The project has reached a record 1,273 days and 13.6 million person-hours without a lost time incident.