We are pleased to have reached another significant milestone at the Istanbul Tuzla Data Center, one of the key projects in the ENKA Data Solutions portfolio, which remains among ENKA’s strategic priorities.
As the project continues to progress steadily, key developments include:
- Roof steel fabrication has been fully completed
- Finishing works have reached 65% completion
- Fit-out works for 2 white space areas have been completed
- Fit-out activities across the remaining 4 white space areas are progressing rapidly
- Façade works have reached 50% completion
- Delivery of the main equipment is scheduled for May, with installation activities set to commence immediately thereafter
Driven by strong coordination and the dedicated efforts of our teams, we continue to advance at pace toward our next milestones.