On our Baghdad Besmaya CCPP Project, as of the end of October, 2015, majority of engineering and PO placement of simple cycle scope are completed. Civil construction works have continued and major mechanical erection works have commenced. Civil works of Block – 1 & 2 turbine buildings, LDO storage tanks, GTG & STG pedestals, HRSG foundations, U/G facilities and Block – 1 turbine building structural steel erection works have progressed. GT and Generator units have been delivered to Site, and GT – 1 have been placed on foundation as the major achievement in mechanical works.