ENKA NEWS

Cimtas Pipe will attend TUBE & Steel İstanbul 2019 in Turkey

Tube & Steel Istanbul, where pipe, profile, wire and steeI Industries gather to collaborate, will be held between April 17-20, 2019 at Tüyap Fair Convention and Congress Center. Cimtas Pipe would be delighted to host its guests at Booth 216 (Hall 2). Cimtas Pipe

Cimtas Pipe Continues to Make Strides in the Offshore Market

Cimtas Pipe – LSAW Pipe Works, has obtained the DNVGL-ST-F101 Submarine Pipeline Systems Conformity Certificate, one of the demanding requirements of the offshore market for LSAW pipe manufacturing, after a successful audit process. In the wake of the certification process, our capabilities have also been duly recognized after the audit process conducted at LSAW Pipe …

Injection System for Petkim Aliağa Complex Water Treatment Plant, Turnkey Project

Cimtas Pipe has completed partial detail engineering, procurement, prefabrication, installation and start-up activities within the scope of civil, mechanical, piping, electrical, instrumentation, pressure vessels, valves and pump skids of PAC and PE Injection System for Petkim Aliağa Water Treatment Plant. The turnkey project has been completed within 11 months with the lead of Cimtas Pipe …

Umm Qasr BMT Yard-5 Quay Wall & Marine Works in Iraq reached 30%

ENKA’s project of Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Works is progressing at full speed. As of 21 March 2019, a total of 754 Precast Blocks had been fabricated and 80.72% of material had been dredged from the port basin. The rate of overall completion on the project reached …

Çimtaş has successfully delivered Steel Shafts to the 1915 Çanakkale Bridge Project

Çimtaş, a fully owned subsidiary of ENKA, which was executing the fabrication of all permanent steel structures with a total weight over 90,000 tons for 1915 Çanakkale Bridge Project, has successfully delivered to the project site by sea of 4 ea Steel Shafts, being the first parts fabricated for the project, each with a height …

ENKA Samawa and Dhi Qar CCPP Projects teams have successfully completed one of the major project milestones.

ENKA Samawa and Dhi Qar CCPP Projects teams have successfully completed one of the major project milestones. Accordingly, GE 9E series combustion turbine generators for both projects have been delivered to projects sites by ENKA teams safely. We congratulate both teams for completing this milestone and wish them all the best for the rest of …

The first day of the International Nuclear Power Plant Summit (INPPS), 2019 in Istanbul, Turkey

The first day of the International Nuclear Power Plant Summit (INPPS), 2019 in Istanbul, Turkey.

Samawa Combined Cycle Power Plant Project reached 1,000,000 Man-Hours without LTI

We are pleased to announce that Samawa Combined Cycle Power Plant Project in Basra, Iraq reached 1,000,000 man-hours without lost time incident as of March 04, 2019! We would like to thank all team members who contributed to achieve such milestone, we hope this success will continue until the end of the project.

Cimtas Pipe Fitting Works Delivered the A234 WP92 Tee for El Bracho Gas-Fired Power Plant Project in Argentina

Cimtas Pipe Fitting Works undertook the manufacturing of A234 WP92 Hot Formed TEE, a non-standard, high alloy steel product measuring 28” in diameter and with 19 mm wall thickness as part of the El Bracho GFPP Project in Argentina. Furthermore, all the mandatory tests for A234 WP92 Tee were completed at Cimtas Pipe’s in-house Mechanical …

Umm Qasr BMT Yard-5 Quay Wall & Marine Works in Iraq has reached 26%

As of the end of February 2019, on ENKA’s project of Umm Qasr BMT  Container Terminal Yard-5 Quay Wall and Marine Works in Basra – Iraq the overall progress of completed works including engineering, design, procurement, construction activities was determined to be 26%. For project’s details: Umm Qasr BMT Yard-5 Quay Wall & Marine Works   …