The Produced Water 2 Facility project in Iraq, on which ENKA had started working in 2019, was 61% complete by the end of November 2021.
As ENKA is an EPC contractor of the project, ENKA Design & Engineering Center is responsible for the design and engineering works, which have been completed substantially. In addition, procurement and construction activities are ongoing and the completion rates for procurement and construction stand at 83% and 10% respectively.
By the end of November 2021, the project has been under way for 731 working days and 430,000 person-hours have been expended without lost time incident.