As of October 2022, ENKA has completed the engineering works for the West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project, which it is undertaking in Basra, Iraq with its in-house resources. The procurement work scope of the project is almost completed, and the progress on construction stands at 69%. A total of 1,065 working days and 1.3 million person-hours were expended without lost time incident on the project.