Geotechnical works undertaken by ENKA’s subsidiary Kasktaş within the scope of the ICITY Tower project in Moscow City in Russia, continue in accordance with the work schedule.
The execution of the shoring system was commenced after the completion of piles foundation under the first skyscraper of the project, which was started on February 20th, 2021. The excavation of the shoring pit was carried out after the completion of pipe pile and Berliner wall installation works in the shoring system on August 10th, 2021. In July, pipe support system and dewatering systems installation in the shoring system was started. As of mid-September, 80% of the bored piles, 40% of the pipe piles and 40% of the excavation works in the project have been completed. The remaining works within the project are planned to be completed by April 2022.