As ENKA, we are proud to announce that the construction continues to advance steadily at our Istanbul Tuzla Data Center as the project moves closer to operational readiness.
Civil works for the main building and all auxiliary structures have been completed. Facade, architectural fit-out and site infrastructure works advances in parallel as the project progresses toward operational readiness.
Mechanical, electrical and plumbing (MEP) installations are progressing alongside the installation of critical systems, while mechanical testing activities have commenced. As interior fit-out and equipment installation continue, the project is progressing through the next phase of operational preparation.
Medium-voltage testing has been successfully completed, while Level 2 commissioning walkdowns, mechanical system flushing and commissioning activities are advancing as planned, with backfeed energization and equipment commissioning scheduled for mid-August.
Each milestone brings the facility closer to delivering resilient and carrier-neutral digital infrastructure, built with ENKA’s engineering standards and a continued commitment to quality, safety and operational excellence.