The Dradenau Combined Heat and Power Plant project, the construction of which we are carrying out with Uniper in Germany, is based on a 2x2x1 configuration equipped with two Siemens SGT-800 gas turbines, one steam turbine, and two heat recovery steam generators (HRSG) with one additional gas steam generator.
The plant’s capacity will include an electrical output of 180 MW and a district heating capacity of 260 MW. The project is progressing, with an overall completion rate of 30.5%. The engineering phase has reached 76% completion. Piling works are nearly completed, currently standing at 90% completion.
Furthermore, we have already committed 75% of the value of procurement packages, showcasing our strong dedication to ensuring the project’s success.