The Corridors 8 & 10d Motorway Project in North Macedonia is progressing under the execution of the ENKA–Bechtel Joint Venture, with more than 2,000 people, including subcontractors, actively working across various project areas.
In Sections 1 ,2 and 4, earthworks and construction of structures are advancing, while drainage works are also ongoing. As of the end of December 2025, a total of 5 million m³ of excavation, 1.6 million m³ of fill, 955,000 tons of aggregate production and 93,500 m³ of concrete works have been completed.
Accommodation camp construction has been completed in Sections 1 and 4, with total active capacities of 1,304 people in Section 1 and 784 people in Section 4.
As of the end of December 2025, the project has reached a record of 1,030 days and 9,964,412 person-hours without a lost time incident.