Infrastructure

Progress of The Morava Corridor Motorway Project as of August 2026

Progress of The Morava Corridor Motorway Project as of August 2026

The Morava Corridor Motorway project, being undertaken by the Bechtel-ENKA JV, is progressing rapidly and will provide a vital link between Central Serbia and the Pan-European Corridors 10 and 11.ar The project involves a 112.4 km dual-carriageway motorway divided into Continue reading
Learn more
Progress of the San Juan Cruise Port Development Project as of Mid-July 2026

Progress of the San Juan Cruise Port Development Project as of Mid-July 2026

ENKA continues to make significant progress on the San Juan Cruise Port Development Project in Puerto Rico. This landmark development will modernize the Port of San Juan’s critical infrastructure, strengthen operational efficiency, increase capacity, and position the port as a Continue reading
Learn more
Progress of The Corridor 8 & 10d Motorway Project as of June 2026

Progress of The Corridor 8 & 10d Motorway Project as of June 2026

The Corridors 8 & 10d Motorway Project in North Macedonia continues to make progress under the execution of the ENKA-Bechtel Joint Venture. Currently, more than 1,550 personnel, including subcontractors, are actively working across various project areas. In Sections 1,2 and Continue reading
Learn more
ENKA-Bechtel JV Opens 28.7 km Section of the Morava Corridor Motorway

ENKA-Bechtel JV Opens 28.7 km Section of the Morava Corridor Motorway

On June 26, 2026, the Morava Corridor Motorway Project of ENKA-Bechtel JV (BEJV) opened 28.7 km section of the motorway from Adrani to Preljina and extended the total length of the opened section to 100.3 km! The Morava Corridor Motorway, Continue reading
Learn more