Kazan 250 MW Combined Cycle Power Plant project, which ENKA is executing in consortium with Siemens in Russia, is progressing at full speed.
As of 1st of November, 2021, while the overall progress of the project including design, procurement and construction activities stands at 34%, the progress of construction works at the project reached 22%. The project reached 1,784,711 person-hours without lost time incident and a total of 668 employees are working at the project site.