The West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project of ENKA in Basra, Iraq is 93% complete as of December 2022. The project reached 1,500,000 person-hours / 1,127 days without lost time incident.
The PW2 project will produce 210,000 barrels of water per day of outlet stream treated produced water in order to meet forecast produced water across West Qurna 1 Degassing Stations 6, 7 and 8.