In Sections 1 and 2A, approval for the urban plan has been obtained, access to public parcels has been provided and the construction of associated works has commenced.
In Section 4, approval processes are currently underway, and work on public parcels will commence upon approval. Subsequent to the employer completing expropriation works on ongoing private parcels, works are anticipated to commence on private parcels in Sections 1, 2, and 4.
On September 12, 2023, in Section 2, a significant milestone in the project was marked with the inaugural blasting ceremony with the participation of important figures from the Government of North Macedonia.The ceremony was attended by the Deputy Prime Minister, Minister of Transport and Communications, and senior executives of the Bechtel-ENKA team.