Currently, over 3,500 employees are working with a superior effort for a wide range of works. 17 million m3 of excavation, 6.5 million m3 of fill and 220,000 m3 of concreting works have been completed. In the Sector 1, the majority of earthworks have been completed, and drainage and finishing works are in progress. Piling, foundations, elevations, beam installation and deck construction works are advancing at a rapid pace by the structure team. In the Sector 2, excavation and fill works, embankment scour protection works and piling, foundation and elevation works for bridges are progressing contemporaneously. Preparations of precast girders are also ongoing. In the Sector 3, beam productions have started. Excavation and fill works, embankment scour protection works and piling, foundation and elevation works for bridges are still progressing. In addition, Adrani camp construction is ongoing.
Bechtel-ENKA JV provided HSE and quality trainings to all personnel working on the project according to the requirements of different disciplines, thereby 6 million person-hours were achieved without any lost time incident (LTI).