Recently ENKA Besmaya team has successfully achieved critical milestones at 1,500 MW Baghdad Besmaya Combined Cycle Electrical Power Station Project:
• First Fire of GTG 11 on December 14th, 2016
• Synchronization of GTG 11 on December 19th, 2016
• Base load operation of GTG 11 on December 19th, 2016
ENKA Besmaya team is planning to perform first fire operation on GTG 12 before the end of December, 2016.