The progress in civil works has achieved to 86% progress. There has been 97% progress in the reinforced concrete works within civil works, and the façade cladding of the Riegel building has been completed. On the other hand, the architectural works, which are progressing efficiently in the completed buildings, have reached 35% progress.
The delivery of all structural steel to the site is ongoing according to the installation plan. To date, 1,850 tons of steel have been installed, with the gas turbine building and cable/pipe bridges completed. It is anticipated that the main structural steel assembly will be largely completed within the year 2024.
The installation of main and auxiliary mechanical equipment, along with pipe installation and welding work, is progressing as planned.
Electrical, instrumentation & controls works subcontractor continues with the installation of transformers, panels and cable trays. In addition, as of July 2024, cable pulling work has commenced.