By the mid of March 2020, a completion progress of 3GP Mechanical, Electrical and Instrumentation Installation works in Tengiz, Kazakhstan reached 25%.
The major site accomplishments of the project include the completion of 49 module stacks and 27 modules set on foundation, the erection of 3,900 tons of structural steel, the fabrication of 3,500 tons of pipe as well as 18,000 m of pipe installation at site.
Furthermore, 49 ea major mechanical equipment had been installed and 9,000 m2 equipment insulation had been completed. 4 Major Building structural steel erection and cladding works are in progress.