In Section 1, significant progress has been made in the construction of the accommodation camp. As of November 2, 2024, the first phase of the accommodation has commenced, housing 256 personnel. Additionally, the construction of the structures is currently underway, while earthworks have begun on the side road.
In Section 2, earthworks and the construction of structures are progressing, with drainage works now underway. Additionally, the construction of the crusher for aggregate production and the concrete batch plant has been successfully completed.
In Section 4, earthworks and the construction of structures continue to progress, and drainage works have also commenced. Furthermore, the construction of the concrete batch plant has been successfully finalized.
In accordance with the traffic management plan for the construction of motorway route, improvement and development works on the diversion route have been completed between km 14+500 and km 20+800. Traffic was successfully diverted and the traffic management measures were implemented.
Throughout Section 4, the identification and clearance of materials defined as Unexploded Ordnance (UXO) are ongoing at the project site by the North Macedonian authorities.
As of the end of November 2024, the highest number of 634 days and 2,898,939 person-hours without a lost time incident were reached on the project.