The motorway features 11 interchanges, 56 bridges, 29 overpasses, 28 underpasses, and extensive embankment scour protection works, flood protection measures and long river diversions, dykes and construction of new river bed due to the wide flood plain of West Morava river. Along the motorway route, the plan is to construct the telecommunication cable ducting through which optical cables will be laid. The goal of the digital corridor is to provide a fast and reliable exchange of information so as to enable safe traffic and comfortable use of the motorway.
As of June 2021, the project has ramped up in the Sector 1 and advanced works are ongoing in the Sector 3. Currently, 1,500 personnel are working for the project and approximately 2 million m3 of excavation, 200,000 m3 of fill and 20,000 m3 of concreting works have been completed. The 1st main camp for 1,410 people is operational since February 5th, 2021 and construction works for the 2nd main camp for 1,000 people are planned to be started in the coming months.