As of 31st of December, 2021; the overall progress of the Kazan 250 MW CCPP project, which ENKA is executing in consortium with Siemens in Tatarstan, the Russian Federation, including design, procurement and construction activities stands at 41%, and the progress of construction work is 30%.
The project reached 2,230,000 person-hours without lost time incident and a total of 712 employees are working at the project site.