We are pleased to announce that Samawa 750 MW Combined Cycle Power Plant Project in Iraq, which ENKA is executing in consortium with GE, has successfully achieved a milestone – GT4 unit was synchronized and handed over to the client, MoE, following the completion of tests on March 9th 2021. The GT4 unit on Samawa project was the last GT unit handed over to MoE on Samawa and Dhi Qar projects being executed in parallel. We would like to thank all team members who contributed to achieving such milestone.