As of the end of June 2025, physical progress has reached 17.63% at the İzmir site and 17.15% at the İzmit site.
Following the completion of ground improvement works and construction permits secured, construction activities on site are planned to commence in August 2025.
Purchase orders for vendor packages – including rotating equipment, pressure vessels, heat exchangers, columns, and control systems – have been placed, and fabrication activities are progressing rapidly in line with the project schedule.
Upon the successful completion of commissioning, both facilities are scheduled to be handed over to the Client in the first quarter of 2027.
We remain committed to delivering engineering excellence with the highest standards in quality and safety at every stage of the project.