ENKA is currently working on the Phase 2 of the High-Technological Multifunctional Medical Complex in St. Petersburg, Russia signed on October 19th 2020, the scope of which includes structural concrete works of 22,640 m² underground carpark, 6,383 m² Oncology Center till ±0.00 level and 14,696 m² Multifunctional Medical Center till ±0.00 level.
The Phase 2, with a total of 780 employees working on the project, has reached the overall progress of 20% as of February 2021 and is planned to be completed in July 2021.
ENKA successfully completed the Phase 1 work scope of the project on June 15, 2020 as planned, along with measures taken against the pandemic. The Medical Complex covering an area of more than 200,000 m² is scheduled to start operating in 2022 and will include an oncology center, a multidisciplinary clinic, a rehabilitation and sports medicine center, an educational complex and a nuclear medicine center.