Oil, Gas & Petrochemicals

Progress works on Produced Water 2 Facility Project in West Qurna 1

Progress works on Produced Water 2 Facility Project in West Qurna 1

The West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project of ENKA in Basra, Iraq is 98% complete as of March 2023 and will be handed over to the client, ExxonMobil Iraq Limited, at the end of April 2023. Continue reading
Learn more
South Caucasus Pipeline Expansion (SCPX) Project

South Caucasus Pipeline Expansion (SCPX) Project

Between 2014 and 2019, a joint venture of ENKA and Bechtel worked on the South Caucasus Pipeline Expansion (SCPX) Project, which was designed to increase the volume of gas flowing from the Shah Deniz field in the Azerbaijan sector of Continue reading
Learn more
Progress of 3GP Mechanical, Electrical and Instrumentation Installation Works Project as of December 2022

Progress of 3GP Mechanical, Electrical and Instrumentation Installation Works Project as of December 2022

By the end of December 2022, the 3GP Mechanical, Electrical and Instrumentation Installation Works Project undertaken by Senimdi Kurylys LLP (ENKA-Bechtel JV) in Tengiz, Kazakhstan reached 97% completion. A total of 4,030 employees were working on the project, and 5.8 Continue reading
Learn more
Progress of West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility as of December 2022

Progress of West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility as of December 2022

The West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project of ENKA in Basra, Iraq is 93% complete as of December 2022. The project reached 1,500,000 person-hours / 1,127 days without lost time incident. The PW2 project will produce Continue reading
Learn more