• 01
  • 02
  • 03

Civil, Mechanical, Electrical, Pre-Com&Commissioning Works on EPC-3 Island

The ENKA-MSS joint venture (JV) was awarded the contract by NCOC in May 2016. It involves the execution of civil, mechanical, electrical, pre-commissioning and commissioning works on EPC-3 Island in the Kashagan area of the Caspian Sea.

EPC-3 Island had previously been constructed by ENKA in 2007 for the client’s drilling ctivities. At the beginning of 2016, ENKA-MSS JV signed a contract with the client for re-configuration works.

All works under this contract were commenced in May 2016 and completed early 2017 and EPC-3 Island has been producing oil and gas since February 2017 via main production and processing Complex, D-Island, which is also known as Hub-1.

Project Description

Civil, Mechanical, Electrical, Pre-Com&Commissioning Works on EPC-3 Island

    Project Features

    Scope of Work
    Civil, Mechanical, Electrical, Pre-commissioning & Commissioning Works
    Client
    North Caspian Operating Company N.V. (NCOC)
    Key Quantities
    Precast Element Fabrication and Transportation 6,912 ea
    Excavation and Sand bedding 7,300 m3
    Backfilling 3,900 m3
    Installation of Precast Elements 6,912 ea
    In situ Concrete Works (Manifold module foundation, open drain tank, trenches, ducting etc..) 1,253 m3
    Installation of Skid Beam 109 ton
    Supply and Filling of Haulage Material 7,150 ton
    Dismantling & Waste Materials Removal 8,750 ton
    Gravel Placement and Final Compaction 5,300 m3
    Grouting 19 m3
    Sealing 1,570 lt
    Painting 169 m2
    Permanent Fence Installation 1,020 m
    Project Duration
    Start Date 05.05.2016
    Finish Date 13.03.2017
    Duration 10 Months

    Location

    Kashagan, North Caspian Sea, Kazakhstan
    ENKA SCOPE OF SERVICES

    Within the scope of the contract, ENKA-MSS JV carried out the survey work, precast and in-situ concrete works, excavation and backfilling activities, the load-in and installation of major equipment provided by the client, mechanical completion, electrical, pre-commissioning & commissioning and start-up support works.

    ENKA-MSS JV provided all the construction and commissioning equipment, marine vessels, personnel and materials necessary for the execution of the works excluding their design. However, permanent project materials such as production modules and pumps, and some marine vessels including an accommodation vessel and transportation barges are provided by the client. ENKA also provided accommodation vessel during peak period of the project.

    Related Projects

    FGP – Wellhead Pressure Management Project – Core Substation ME&I Installation

    FGP – Wellhead...

    Current Kazakhstan Oil,...
    Civil, Mechanical, Electrical, Pre-Com&Commissioning Works on EPC-3 Island

    Civil, Mechanical,...

    Completed Kazakhstan...
    FGP – Cargo Transportation Route Channel Works of Caspian Sea

    FGP – Cargo...

    Completed Kazakhstan...
    FGP 3GP Mechanical, Electrical & Instrumentation Installation Works

    FGP 3GP Mechanical,...

    Current Kazakhstan Oil,...