• Photo 1
  • Photo 2
  • Photo 3

FGP Multi-Well Pads Civil Installation

The Future Growth Project Multi-Well Pads Civil Installation Project is being carried out for TengizChevroil Limited (TCO).

The work to be carried out under the project includes site preparation, piling and civil works for the production of well pads WP 52-1, WP 52-2, WP 53-1, WP 53-2 and WP 54-1, for metering stations MS 52, MS 53 and MS 31, and for a 110/35kV substation, a 35/6kV substation, the central field manifold, the field operations office and the main manifold areas.

Works carried out under the project within the year 2016 included road construction, worksite clearing and grubbing, site preparation, excavation, installation of grounding, construction of wellhead cellars, pile driving, pile testing and cropping, construction of pile cap and pre-cast foundations, construction of emergency flare pits, construction of reserve and technical water pits, and the construction of an HDPE technical water line.

Project Description

FGP Multi-Well Pads Civil Installation

  • Construction

Project Features

Scope of Work
Construction
Contractor
BECHTEL & ENKA Joint Venture (50 %)
Client
Tengiz Chevroil Limited / KPJV (Kazakh Projects Joint Venture)
Key Quantities
Concrete Driven Pile 2,700 ea
Excavation 45,000 m³
Fill 520,000 m³
Concrete 8,500 m³
HDPE Pipeline 8″ – 6,600 m
Project Duration
Start Date 01.11.2015
Finish Date 31.01.2019
Duration 40 Months

Location

Tengiz, Republic of Kazakhstan

Gallery

Related Projects

FGP – Wellhead Pressure Management Project – Core Substation ME&I Installation

FGP – Wellhead...

Completed Kazakhstan...
Civil, Mechanical, Electrical, Pre-Com&Commissioning Works on EPC-3 Island

Civil, Mechanical,...

Completed Kazakhstan...
FGP – Cargo Transportation Route Channel Works of Caspian Sea

FGP – Cargo...

Completed Kazakhstan...
FGP 3GP Mechanical, Electrical & Instrumentation Installation Works

FGP 3GP Mechanical,...

Current Kazakhstan Oil,...