Khabarovsk Refinery Hydroprocessing Project

ENKA was awarded the contract in September 2011, for the electro-mechanical installation work on the Khabarovsk Refinery, in the Russian Federation.

The Khabarovsk Refinery Hydroprocessing Project consists of a major expansion of the existing Khabarovsk refinery, to increase plant capacity, improve performance and address both Russian and international requirements for the reduction of the sulphur content of kerosene and diesel products.

The work included new combined Hydrocracking, Hydrotreating and Hydrogen Units. The associated utilities and offsites, together with the associated upgrades and infrastructure modifications and interconnecting pipe racks were also included.

The scope of the project also consisted of all related pre-commissioning activities, such as motor run tests, loop checks, coupling alignment and pump sealing.

Project Description

Khabarovsk Refinery Hydroprocessing Project

  • Structural Steel Installation
  • Mechanical Erection Works
  • E&I Installation Works
  • Pre-Commissioning & Commissioning

Project Features

Contract Type
Lump Sum & Fixed Unit Rates
Scope of Work
Structural Steel Installation, Mechanical Erection, Electrical & Instrumentation Installation Works, Pre-Commissioning & Commissioning
Client
Alliance Oil Company Ltd.
Contractor
EPC Contractor: Technicas Reunidas – Spain
Key Quantities
Structural Steel Erection4,820 tons
Piping Prefabrication and Erection3,180 tons
Mechanical Installations3,000 tons
Cable Ladder / Cable Trays54,950 m
Cable Laying Works466,500 m
Painting86,900 m2
Pipe Insulation57,900 m
Equipment Insulation4,450 m2
Project Duration
Start Date01.01.2012
Finish Date30.04.2014
Duration28 Months

Location

Khabarovsk, Russian Federation
UNIQUE CHALLENGES

The project was effectively a ‘brownfield’ project. The hydrogen unit was constructed on a site previously occupied by a crude distillation unit. Brownfield nature of the work, compact plot area, rough climate, and performance of works around operating plant created unique challenges for the project team. ENKA utilized construction best practices, its vast winterization experience, and extensive planning to address the challenges.

Khabarovsk Refinery is located near the center of Khabarovsk City, surrounded by heavily populated urban neighborhoods. Very limited area within the jobsite was allocated for laydown and temporary construction facilities. ENKA set up various temporary camps in and around the city and housing and transportation issues were mitigated by establishing a strong team to enhance workforce availability and retention. ENKA worked in compliance with European as well as Russian norms and standards for the execution of the project. Several high pressure and high temperature tie-ins have been completed successfully resulting in excellent safety performance.

ENKA SCOPE OF SERVICES

ENKA was engaged by Technical Reunidas to provide structural, mechanical, piping, electrical, instrumentation, painting and insulation construction services for the project including pre-commissioning and commissioning of three units, namely hydrocracking, hydrotreating and hydrogen production. The project workforce reached 1,400 people during the peak periods of the work.

SIGNIFICANT FEATURES AND ACCOMPLISHMENT
  • First major expansion to the refinery built in 1930s
  • Refining capacity increased to 90,000 bpd
  • Modernization enabled the refinery to capture higher margins on sales of oil products and to preserve its position in domestic and international markets by complying with the high quality standards
  • 6.04 million person-hours without a Lost Time Incident.

Gallery

Related Projects

Produced Water Treatment Facility

Produced Water Treatment...

Basrah Current Energy...
FGP – Wellhead Pressure Management Project – Core Substation ME&I Installation

FGP – Wellhead...

Completed Kazakhstan...
Civil, Mechanical, Electrical, Pre-Com&Commissioning Works on EPC-3 Island

Civil, Mechanical,...

Completed Kazakhstan...
FGP – Cargo Transportation Route Channel Works of Caspian Sea

FGP – Cargo...

Completed Kazakhstan...