• 01

STADE LIQUEFIED NATURAL GAS (LNG) REGASIFICATION TERMINAL

CLIENT

Hanseatic Energy Hub GmbH

SCOPE OF WORK

Electromechanical Assembly Works including piping prefabrication

SECTOR

Oil, Gas & Petrochemicals

LOCATION

Stade, Lower Saxony, Germany

PROJECT DURATION

April 2023 – September 2027

Project Description

ENKA’s wholly owned subsidiary Entrade GmbH, in a consortium formed together with Técnicas Reunidas and FCC Industrial, has signed an EPC (Engineering, Procurement and Construction) contract with the Hanseatic Energy Hub company for the Liquefied Natural Gas (LNG) Regasification Terminal to be built at the Stade Industrial Park situated on the banks of Elbe River, Lower Saxony, Germany.

The contract is for the design and construction of a new storage and regasification terminal for liquified gases, featuring unloading facilities on a newly built modern energy port at Stade.

The land on which the facility will be built belongs to the large chemical company, Dow Chemicals, which is participating in the project as one of the development partners. The terminal will utilize Dow’s industrial waste heat and therefore will be able to regasify the gases without additional CO2 emissions.

The terminal is an important element of Germany’s current energy policy, as one of its main objectives is to diversify its natural gas supply with liquefied natural gas (LNG) and green gases while preparing for the market ramp-up of hydrogen.

The terminal, which will have a nominal annual capacity of 13.3 billion m3, involves a total investment of 1 billion Euros and the share of Entrade GmbH is approximately 25%.

Following the first phase of 5 months for preliminary and engineering works, the second phase, the main works, is planned to commence with the final investment decision to be taken by the Client.

ENKA Scope of Services

Entrade GmbH, a subsidiary of ENKA will perform the electromechanical assembly works of the project including piping prefabrication. Scope of works to be carried out under Entrade’s responsibility will be summarized as mechanical and electrical equipment erection works, steel structure erection works, electrical and instrumentation works, piping fabrication and erection works, painting and fireproofing, insulation, scaffolding, pre-commissioning and testing works. Optionally, Entrade will also provide supervision and manpower support during the commissioning phase. Pipe spool prefabrication of the Plant will be carried out at ENKA subsidiary Cimtas Pipe’s facilities, and the spools will be delivered to Site for its installation.

Key Quantities

Steel structure 5,800 tons
Metallic piping prefabrication 125,000 dia-inch
Metallic piping erection 118,000 dia-inch
Non-metallic piping erection 26,000 dia-inch
Pipe supports 753 tons
Equipment erection 2,100 tons
Insulation 54,000 m2
Painting 60,000 m2
Fireproofing 2,800 m2
Electrical and Instrumentation cabling 780,000 lm

Related Projects

Low Carbon Hydrogen Production Plant (HPP1)

Low Carbon Hydrogen Production Plant (HPP1)

Current Oil, Gas & Petrochemicals United Kingdom
Propylene Splitter Unit Project – İzmit & İzmir Refineries

Propylene Splitter Unit Project – İzmit & İzmir...

Current Oil, Gas & Petrochemicals TÜRKİYE
Stade Liquefied Natural Gas (LNG) Regasification Terminal

Stade Liquefied Natural Gas (LNG) Regasification Terminal

Current Germany Oil, Gas & Petrochemicals
West Qurna I Produced Water 2 Facility

West Qurna I Produced Water 2 Facility

Completed Iraq Oil, Gas & Petrochemicals