WEST QURNA-I INITIAL OIL TRAIN (IOT) PROJECT

CLIENT

ExxonMobil Iraq Limited (EMIL)

CONTRACTOR

ENKA – KentzGlobal Joint Venture

SECTOR

Oil, Gas & Petrochemicals

LOCATION

Basra, Iraq

SCOPE OF WORK

Turn-key Design & Engineering, Procurement, Construction, Testing & Commissioning, Start-up

PROJECT DURATION

August 2015 – February 2020

Project Description

ENKA was awarded a contract by ExxonMobil Iraq limited (EMIL) in July 2015 for a new oil processing facility, called Initial Oil Train (IOT), to increase production at its West Qurna 1 (WQ1) Oil Field in Iraq. The end-user of this new facility is Basrah Oil Company (BOC) of Iraq.

West Qurna is one of the largest oil fields in Iraq with an estimated 43 billion barrels of recoverable reserves. In January 2010, EMIL, an affiliate of Exxon Mobil Corporation, signed an agreement with BOC of Iraq Ministry of Oil to rehabilitate and redevelop the WQ1 field. Facility is located approximately 50 km north-west of Basrah in south-eastern Iraq. WQ1 is one of three segments of one large oil field complex located in southern Iraq that is bounded by the Rumaila Field to the south and the West Qurna II field to the north.

The facility, located in the province of Basrah, is designed to process full well stream fluids from the production wellhead area and separate them into associated gas, untreated produced water and stable product crude for export. The contract required modularization of the facility to the maximum possible extent with consideration of the logistics constraints.

Initial Oil Train (IOT) Project was selected as Engineering News-Record (ENR) Global Best Project 2020 in the Power / Industrial Category and recieved a “Distinction Prize” and the “Best in Country Award – The Republic of Türkiye” by the British Safety Council at the International Safety Awards in 2019

Unique Challenges

The site and camp are in areas contaminated with Unexploded Ordnance and Explosive Remnants of War. Clearance activities were conducted by the Owner. Movements were allowed in designated areas only.

Toxic gases constituted another risk. Critical levels of hydrocarbon emissions are occasionally observed. H2S, LEL, CO and SOx monitoring was conducted constantly.

The challenge of executing the project at multiple locations (i.e. engineering offices in UAE, USA, India, Türkiye and Canada, fabrication yards in UAE, Türkiye, Italy, Luxembourg, construction site in Iraq) with different time zones and day/night shifts, was overcome by extensive planning and proper interface management.

ENKA Scope of Services

ENKA, with its regional partner Kentz, provided the front-end engineering design (FEED), detailed design engineering, procurement, fabrication, construction, commissioning and start-up assistance to EMIL for the new facility, which is capable of producing an annual average of 100,000 stock tank barrels of crude oil per day and constructed adjacent to the existing degassing station facility DS8.

ENKA fabricated the pipe rack modules of the facility through its subsidiary Çimtaş. The supply, fabrication, testing and trial assembly works were carried out at the Çimtaş Module & Shipyard Facilities in Gölcük – Kocaeli, Türkiye, and the modules then were directly shipped to site.

Significant Features and Accomplishments

  • The project was selected as Engineering News-Record (ENR) Global Best Project 2020 in the Power / Industrial Category.
  • Thanks to management commitment and full engagement of the highly-multinational team, the project achieved its zero-accident target, clocking up 4,533,928 person-hours without a lost time incident. ENKA’s HSE Management System at West Qurna I – IOT Project, was recognized and awarded by the British Safety Council with “Distinction” and “Best in Country Award – The Republic of Türkiye” at the International Safety Awards competition in May 2019.
  • As part of ENKA’s commitment to promote the Iraqi content in the project and amid political pressures throughout the project, Iraqi workforce has been employed to the maximum possible extent.

Key Quantities

Earthworks 34,214 m3
Concrete 4,250 m3
Structural Steel 500 tons
A/G Piping 1,500 tons
Cabling 178,887 lm
Mech. Equipment 3,202 tons

Gallery

Related Projects

Low Carbon Hydrogen Production Plant (HPP1)

Low Carbon Hydrogen Production Plant (HPP1)

Current Oil, Gas & Petrochemicals United Kingdom
Propylene Splitter Unit Project – İzmit & İzmir Refineries

Propylene Splitter Unit Project – İzmit & İzmir...

Current Oil, Gas & Petrochemicals TÜRKİYE
Stade Liquefied Natural Gas (LNG) Regasification Terminal

Stade Liquefied Natural Gas (LNG) Regasification Terminal

Current Germany Oil, Gas & Petrochemicals
West Qurna I Produced Water 2 Facility

West Qurna I Produced Water 2 Facility

Completed Iraq Oil, Gas & Petrochemicals