THE NASSAU CRUISE PORT AT PRINCE GEORGE WHARF, MARINE AND UPLAND WORKS

CLIENT

Nassau Cruise Port Ltd 

SCOPE OF WORK

Lump Sum, Turn-key

SECTOR

Infrastructure

LOCATION

Nassau, The Bahamas

PROJECT DURATION

Marine Works: November 2020 – July 2022

Upland Works: May 2021 – May 2023

Project Description

The Bahamas Government is determining strategies to maximize cruise tourism by developing the existing port at Prince George Wharf – Nassau Cruise Port. Renovation and the expansion of the port will increase the capacity and allow passengers a better experience.

Nassau Cruise Port project is developing Nassau into one of the great waterfronts of the world. The project involves the redevelopment of the port. The project will enhance the passenger experience and provide additional business opportunities for the local population. The project will also include the building of a new terminal building; the creation of an event and entertainment area; investments in retail facilities for new and expanding Bahamian brands; and the design and construction of new food and beverage facilities. It will integrate the port into Bay Street and downtown Nassau, with the expectation that it will act as a catalyst for the wider development of the downtown area.

ENKA signed the contract for Marine Works of the Nassau Cruise Port project in June 2020 and Upland Works in May 2021.

The Marine and Upland Works contracts include EPC works for the expansion of the existing Cruise Pier, combi-wall works on Prince George Wharf, construction of 2 new marinas for tour boats, dredging, expanding the port area by reclaiming and renovating / refurbishing of existing piers, arrival building, Junkanoo museum, Signature restaurant, amphitheatre, 3 pier buildings, canopies, town square, market place, landscape works and all relevant construction, mechanical, electrical and architectural activities.

With the completion of all construction activities, Nassau Cruise Port is expected to welcome over 4 million passengers in 2023.

Nassau Cruise Port Development Project in the Bahamas was honored with the Best Project award in the Airport/Port category in ENR’s 2023 Global Best Projects Competition

ENKA Scope of Services

PHASE 1:

  • Dredging to accommodate Oasis and Epic class cruise vessels;
  • Extending the cruise pier 720 feet to the east to create an additional berth;
  • Creating a berth for mega-yachts at the cruise pier extension;
  • Rehabilitating the existing cruise pier, passenger pier, and mooring dolphins;
  • Rehabilitating connecting structures 1 and 2;
  • Retrofit and extending Prince George Wharf (PGW);
  • Reclamation and stabilization of additional land near the West marina; and
  • Creating the East and West Marinas.

PHASE 2:

  • Arrival Building: 3,492 m2
  • Signature Restaurant: 700 m2
  • Junkanoo Museum: 388 m2
  • New Town Square: 1,947 m2
  • The Marketplace: 869 m2
  • Amphitheater: 2,712 m2
  • Pier & Carpark Shading Canopy
  • Pier Buildings: 992 m2
  • External Works (hardscaping and landscaping): 38,000 m2

Key Quantities

Dredging for OASIS Class ship 175,000 CY (131,733 m3)
Reclamation 174,500 CY (133,415 m3)
Construction of new deck on pile cruise pier 727’-6” x 100’ (222 x 30.5 m)
New east marina deck on pile, with berthing for tour boats 16 ea
New west marina deck on pile and inner harbor with berthing for tour boats 15 ea
New reclaimed area 143,000 SF (13,300 m2)
Combi wall 2000’ LF (610m)
Tubular pile 4,900 ton
Sheetpile 1,087 ton
Tie-rod installation consisting of 204 pieces 4,088 m (13,412,07 ft)
Pre-stressed Precast Panels in 925 pieces 3,812 CY (2,915 m3)
In-situ concrete 7052 CY (5,392 m3)
Precast concrete beams 2,260 CY (1,728 m3)

Gallery

Related Projects

San Juan Cruise Port Development Project

San Juan Cruise Port Development Project

Current Infrastructure Puerto Rico
Oyu Tolgoi Underground Project

Oyu Tolgoi Underground Project

Current Infrastructure Mongolia
Corridors 8 & 10d Motorway Project

Corridors 8 & 10d Motorway Project

Current Featured Infrastructure North Macedonia