Sirte Bay Hotel and Conference Center consisting of magnificent convention center and tourism complex in Libya was designed to host conferences and guests of high official levels. The center was completed by ENKA at incredible speed in the extraordinarily short period of six months. The contract was on a turn-key basis, with infrastructure, landscaping, and fully furnished and equipped facilities.
SIRTE BAY HOTEL AND CONFERENCE CENTER
Project Description
ENKA Scope of Services
The work included the engineering, procurement, and construction of the following units:
- Four hotel buildings, each comprising four stories of 32,200 m²
- Reception hall of 2,700 m²
- Giant tent-style conference hall of 3,500 m²
- 43 bungalows, and administrative building, restaurant, cafeteria and sports center with a total construction area of 4,750 m²
- Power center, water purification and chlorination plant, parking lot, heliport, and walk ways, with a total construction area of 47,500 m²
- Turn-key construction of 59 high quality villas, fully furnished, including service buildings, roads, and infrastructure in Sirte.
Key Quantities
Excavation | 76,590 m3 |
Filling | 25,500 m3 |
Reinforced Concrete | 33,000 m3 |
Concrete | 17,000 m3 |
Formwork | 79,010 m² |
Steel | 3,060 tons |
Walls | 19,022 m² |
Gypsium Board | 25,720 m² |
Painting | 75,432 m² |
Insulation | 16,873 m² |
Marble | 4,807 m² |
Carpet | 18,423 m² |
Total Construction Area | 52,250 m2 |