The Corridors 8 & 10d Motorway Project in North Macedonia is progressing through the joint efforts of ENKA and Bechtel. More than 2,000 people, including subcontractors, are actively working across various project areas.
In Sections 1,2 and 4, earthworks and construction of structures are advancing, and drainage works are also ongoing. As of the end of September 2025, a total of 4 million m³ of excavation, 1.1 million m³ of fill, 800,000 tonnes of aggregate production and 57,000 m³ of concrete works have been completed.
The construction of accommodation camps in Sections 1 and 4 has been completed.
As of the end of September 2025, the project has reached a record 938 days and 8,151,045 person-hours without a lost time incident.