Progress of Nassau Cruise Port Project in the Bahamas as of March 2022

Progress of Nassau Cruise Port Project in the Bahamas as of March 2022

ENKA picked up the pace on Upland Works of Nassau Cruise Port project in the Bahamas whilst getting closer to the completion of Marine Works. As of end of March 2022, 92.77% progress has been reached in Marine and 14.83% Continue reading
Learn more
Morava Corridor Motorway Project reached 4 million person-hours without LTI

Morava Corridor Motorway Project reached 4 million person-hours without LTI

We are pleased to announce that Morova Corridor Motorway Project in Serbia, which ENKA is undertaking with Bechtel, reached 4,000,000 person-hours / 193 days without lost time incident as of 7 March 2022.
Learn more
Progress of Morava Corridor Motorway Project

Progress of Morava Corridor Motorway Project

As of today, Morava Corridor Motorway Project in Serbia, which ENKA is undertaking with Bechtel, is progressing rapidly in the Sector 1 and Sector 3. Currently, over 2,600 employees are working with a superior effort for a wide range of works Continue reading
Learn more
Progress of Nassau Cruise Port Project in the Bahamas as of December 2021

Progress of Nassau Cruise Port Project in the Bahamas as of December 2021

As of December 2021, the progress of Marine works reached approximately 89% and Upland works stood at 12% on the Nassau Cruise Port project ENKA is undertaking in the Bahamas. The Bahamas Government is determining strategies to maximize cruise tourism Continue reading
Learn more