Progress of the Produced Water 2 Facility Project by the end of 2021

Progress of the Produced Water 2 Facility Project by the end of 2021

ENKA PW2 project team keeps working hard at the project site. As of the end of 2021, on the West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project we are undertaking in Basra, Iraq, the engineering works of which we Continue reading
Learn more
Produced Water 2 Facility Project Progress by the end of November 2021

Produced Water 2 Facility Project Progress by the end of November 2021

The Produced Water 2 Facility project in Iraq, on which ENKA had started working in 2019, was 61% complete by the end of November 2021. As ENKA is an EPC contractor of the project, ENKA Design & Engineering Center is Continue reading
Learn more
3GP ME&I Installation Works Project reached 10 million person-hours without LTI

3GP ME&I Installation Works Project reached 10 million person-hours without LTI

FGP 3GP ME&I Installation Works Project being undertaken by Senimdi Kurylys LLP (ENKA-Bechtel JV) in Tengiz, Kazakhstan reached a major safety milestone with 10 million person-hours / 375 days without a lost time incident as of November 19, 2021. We Continue reading
Learn more
The progress of 3GP ME&I Installation Project in Tengiz as of October 2021

The progress of 3GP ME&I Installation Project in Tengiz as of October 2021

As of the end of October 2021, the completion progress of the 3GP Mechanical, Electrical and Instrumentation Project being undertaken by Senimdi Kurylys LLP (ENKA-Bechtel JV) in Tengiz, Kazakhstan stands at 70%. The number of employees working on the project Continue reading
Learn more