Oil, Gas & Petrochemicals

Produced Water 2 Facility Project Progress as of the end of August 2021

Produced Water 2 Facility Project Progress as of the end of August 2021

The Produced Water 2 Facility project, on which ENKA had started working in 2019, was 50% complete by the end of August 2021. As ENKA is an EPC contractor of the project, ENKA Design & Engineering Center is responsible for Continue reading
Learn more
SOCAR Electromechanical General Construction Works

SOCAR Electromechanical General Construction Works

ENKA signed a 3 year call-off contract with SOCAR in March 2021. The scope includes maintenance, repair and renewal type works in mechanical, electrical, instrumentation and civil disciplines. ENKA performs procurement, prefabrication and construction under individual work packages that take Continue reading
Learn more
BP – BTC Construction and Repair Services

BP – BTC Construction and Repair Services

In 2019, BP and ENKA had signed a call-off contract to fulfill maintenance, repair and renewal works on Baku-Tbilisi-Ceyhan pipeline and associated facilities. Mechanical, electrical, instrumentation and civil disciplines are included in the scope. ENKA successfully performed Landslide Mitigation Works Continue reading
Learn more
The progress of 3GP ME&I Installation works in Tengiz as of June 2021

The progress of 3GP ME&I Installation works in Tengiz as of June 2021

As of the end of June 2021, the completion progress of 3GP mechanical, electrical and instrumentation installation works being undertaken by Senimdi Kurylys LLP (ENKA-Bechtel JV) in Tengiz, Kazakhstan stands at 58.3%. Manpower ramp-up has resumed and the project has Continue reading
Learn more