The progress of 3GP MEI Installation works in Tengiz as of December 2019
By the mid of December 2019, the completion progress of 3GP Mechanical, Electrical and Instrumentation Installation works in Tengiz, Kazakhstan reached 19% and the number of employees working on the project site achieved 2,400 and 3 million person-hours had been Continue reading