Oil, Gas & Petrochemicals

SCPX Project Progress

SCPX Project Progress

SCPx Project is now close to be Mechanically Completed at two of the Worksites, Compressor Station Georgia #1 (CSG-1) and Pressure Reduction & Metering Station (Area 81.) Currently, system hand overs to client’s commissioning teams are on-going with targeting the Continue reading
Learn more
Area81 SCPX 2,500,000 Man-Hours without LTI

Area81 SCPX 2,500,000 Man-Hours without LTI

We are pleased to announce that Area81 Site of SCPX Project in Georgia, reached to 2,500,000 man-hours without lost time incident as of 12.06.2017!
Learn more
Bautino Offshore Projects 3,000,000 Man-Hours without LTI

Bautino Offshore Projects 3,000,000 Man-Hours without LTI

We    are    pleased     to    announce    that    Bautino Offshore Projects in Kazakhstan reached to 3,000,000 man-hours / 943 days without lost time incident as of 1 May 2017!
Learn more
SCPX Project Facilities construction works is on-going at its full speed with reaching its peak manpower…

SCPX Project Facilities construction works is on-going at its full speed with reaching its peak manpower…

Bechtel-ENKA’s SCPX Project construction works is on-going at its full speed. CSG-1 Site Progress is reaching to 80% as being at the final return of construction works with the commencement of Mechanical Completion activities. CSG-2 Site is progressed by 40%. Continue reading
Learn more