Electrical, instrumentation & controls installation works subcontractor commenced installation activities as of February 2024. The first panel assembly has been completed, and cable tray works are ongoing.
The procurement processes for the supply and manufacturing of structural steel for the entire project have been finalized, with deliveries to the site currently in progress. To date, 400 tons of steel assembly works have been completed, with substantial completion of the gas turbine building. It is anticipated that all steel assembly will be finished by the end of 2024.
The order for all raw pipe and fitting materials for spool manufacturing has been placed, and the spool manufacturing is ongoing. Piping installation works have commenced as of February 2024.
A progress rate of 75% has been achieved in civil concrete works, with the completion of concrete works for the Riegel building. Furthermore, architectural works are ongoing and facade installation activities commenced in January 2024.
By the end of April 2024, a total of 667,339 person-hours and 295 days were worked on the project without any lost time incident (LTI).