Future Growth Project (FGP)/Wellhead Pressure Management Project (WPMP). This expansion includes the construction of new greenfield process plants and some brownfield facilities in the work area.
In FGP/WPMP MWP Civil Installation Contract, construction of new roads, mud-reserve and flare pits, bulk backfilling and excavations, HDPE Technical water pipeline installation, precast concrete pile installation and cropping, construction of foundations required for the early greenfield production Multi Well Pads and Metering Stations are carried out.
As of August 2017, more than 4,300 m3 of concrete poured, 5,500 m HDPE pipeline installed, 3,000 ea. precast concrete piles driven, 210,000 m3 bulk filling material backfilled, 7.8 km gravel road constructed on different well pads, metering stations, greenfield & brownfield sites with an overall progress of 54.6% achieved. The project is expected to be completed by the end of October 2018.