The main contract was signed in December 2017 between the General Electricity Company of Libya (GECOL) and the consortium of Siemens Energy Global GmbH & Co. – ENKA İnşaat ve Sanayi A.Ş. (ENKA). The works within the scope of the main contract were successfully completed and handed over to the owner in February 2023.
The project was based on a power island configuration featuring 2 sets of Siemens SGT5-PAC 4000F gas turbines and turbine generators units, providing a gross output capacity of up to 650 MW.
The plant was constructed on a lump sum turnkey basis and the scope of the consortium includes engineering, procurement, construction and commissioning to ensure the power plant operates safely and reliably under all conditions, in accordance with the terms of the EPC contract.
In addition to the main contract scope, the consortium was awarded a variation order in May 2023 for the engineering, procurement, construction and commissioning of a light distillate oil (LDO) treatment plant and a hydrogen generation system.
The gas turbines are dual-fuel engines capable of operating on two types of fuel: natural gas as the primary fuel and light distillate oil as the backup.