ENKA KIRKLARELİ ELEKTRİK ÜRETİM A.Ş. 850 MW NATURAL GAS COMBINED CYCLE POWER PLANT

CLIENT

ENKA Kırklareli Elektrik Üretim A.Ş.

CONTRACT TYPE

Engineering, Procurement, Construction & Commissioning (EPCC)

SECTOR

Power Plants

LOCATION

Kırklareli, Türkiye

PROJECT DURATION

November 2022 – March 2026

Project Description

ENKA Kırklareli Elektrik Üretim A.Ş. has undertaken the construction of the Kırklareli Natural Gas Combined Cycle Gas Turbine Thermal Power Plant (CCGTTPP) project located in Kırklareli city in Türkiye as its own investment.

The power plant will be based on 1x1x1 configuration, equipped with one GE 9HA.02 gas turbine and hydrogen cooled generator (H78), one D650 steam turbine and air-cooled generator (A78), one triple-pressure reheat heat recovery steam generator (HRSG) to be supplied by GE, one air-cooled condenser (ACC), one gas-regulating metering station (RMS) and all associated equipment and systems.

Upon completion, the plant will achieve an output of 850 MW, utilizing natural gas as its fuel source.

Key Quantities

Earthworks1.3 million m3
Structural Concrete72,000 m3
Structural Steel6,350 tons
Wall Cladding17,000 m2
Roof Cladding15,500 m2