• 001
  • 002
  • 003

Sheremetyevo International Airport, Terminal 3

Sheremetyevo International Airport, one of the largest international airports in the Russian Federation, serves more than 40 foreign carriers, in addition to various Russian airlines. Sheremetyevo Airport’s principal carrier is Aeroflot Russian Airlines, the Russian Federation’s largest air carrier, for which Sheremetyevo serves as the base. Initially, the airport had two terminals, Sheremetyevo 1 and Sheremetyevo 2, providing services for domestic and international routes. Aeroflot decided to build a third terminal to serve as Aeroflot’s and its alliances’ international terminal. Terminal 3 has an annual capacity of 12 million passengers. ENKA was awarded the turnkey design and build contract for the project in June 2005.

The terminal building consists of a 6-storey reinforced concrete building. The footprint of the building is 52,000 m2 and the total construction area is 170,000 m2 . The height of the terminal building is 38.5 m, and the roof has a steel structure dome with a diameter of 66 m and a steel main arch with canopies weighing more than 1,800 tons. The building’s facade is composed of glazing, aluminum composite and natural
stone. Apart from the terminal building, major work in the contract includes an apron area of 374,000 m2 ; a multistorey car park for 4,000 cars; a control tower; 12 fixed passenger bridges; various car and bus parks; external facilities, such as a water treatment plant and water supply lines, switch room; infrastructure, including high voltage cable lines, sewage lines, fiber optic cable ducts; construction of the aircraft refueling system, and hard and soft landscaping. Check-in and passport counters and the lounge furniture are also included in the contract work.

Project Description

Sheremetyevo International Airport, Terminal 3

  • Turn-key Engineering
  • Procurement
  • Construction

Project Features

Scope of Work
Turn-key Engineering, Procurement, Construction
Client
OAO Terminal
Consultant
Bovis Lend Lease International Ltd.
Key Quantities
6 storey Terminal Building177,000 m²
3 storey Car park Building332,240 m²
Apron374,000 m²
Access Roads and Flyovers88,000 m²
Total amount of Concrete313,732 m³
Total amount of Rebar19,752 tons
Excavation and earth removal420,833 m³
Backfill including gravel, sand and crushed
aggregate, which were all imported
608,902 m³
Flyover bridge19,750 m²
Highway46,330 m²
Viaduct5,194 m²
Project Duration
Start Date01.06.2005
Finish Date01.11.2011
Duration78 Months

Location

Moscow, Russian Federation
UNIQUE CHALLENGES
  • As the existing airport facilities were in operation throughout construction, extra special care had to be taken with regard to safety, environmental protection and security
  • The project was conducted with due diligence, taking into consideration compliance with Russian norms and also in accordance with the international (IATA) standards on design and engineering
  • Supply and installation of all of the existing utilities (including provision of power, cold & hot water supply) beyond the site borders were also included in the General Contractor’s Scope of Works
  • The refueling system and its connections were included in the General Contractor’s Scope of Works and all works including installation, testing and commissioning were conducted while the main systems of the airport was operational for other terminals
  • Permanent flyovers and access roads to and from the terminal and construction of all connections were conducted without any disturbance to the existing traffic to/from the running terminals.

Gallery

Related Projects

Multifunctional Medical Complex in Gelendzhik

Multifunctional Medical...

Building Works C_Public...
Development of Muscat International Airport Main Contract 3

Development of Muscat...

Building Works C_Public...
The Mausoleum, Mosque, Museum and Library

The Mausoleum, Mosque,...

Building Works C_Public...
Ufa Perinatal Medical Center

Ufa Perinatal Medical...

Bashkortostan Republic...