• 001

TRAKYA NATURAL GAS COMBINED CYCLE POWER PLANT

CLIENT

Turkish Electricity Authority – TEK

CONTRACTOR

Consortium with Alstom (former BBC) ENKA’s share is 35%

SECTOR

Power Plants

LOCATION

Trakya, Türkiye

CONTRACT TYPE / SCOPE OF WORK

Lump Sum Turn Key / Turn-key Engineering, Procurement, Construction, Commissioning

PROJECT DURATION

December1984 – September 1987

Project Description

In the Iate 70’s MTA, Mineral lnvestigation and Research Institute discovered natural gas resources in Trakya, north-west of Türkiye. In early 80’s T.P.A.O., Turkish Petroleum Inc., determined reserves up to 15 billion m3 of natural gas in the same area and soon afterwards the State Planning Organization commenced feasibility studies regarding alternative usages of the exploited gas. The main alternatives were; to use natural gas as raw material in the existing and future fertilizer plants, to change Ambarlı Power Plant from fuel oil fired to natural gas fired, etc. Finally, it was decided to erect a combined cycle power plant to utilize the natural gas in the most favorable way and TEK, Turkish Electricity Authority called for an international turn-key tender.

ENKA – Alstom (former BBC) Consortium was awarded with the contract for 1,200 MW Natural Gas Combined Cycle Power Plant. Depending on the new natural gas source-Gas Pipeline between U.S.S.R. and Türkiye- decision for the 100 % extension of the plant was given and construction works were started in December 1986.

Trakya Natural Gas Combined Cycle Power Plant is the first of its type in Türkiye and produces 7,2 billion kWh electricity per year. The plant consists of 8 gas and 4 steam turbine each having an output of 100 MW and equipped with 2 Heller System Natural Draft Dry Cooling Tower each 135 m high. The plant has a high thermal efficiency (≈51 %) and specific installation cost (cost/kW) is much lower than the comparable conventional steam power plants.

The First Combined Cycle Power Plant Project in Türkiye

ENKA Scope of Services

  • Gas Turbo-Sets, Gas Turbine Building, Erection of 8 Gas Turbines and Auxiliaries, Manufacturing and Erection of 8 Exhaust Ducts and Chimneys (each 35 m. high), Manufacturing and Erection of 8, 125 MVA 10,5 / 380 kV Step­ Up Transformers and Auxiliary Transformers
  • Heat Recovery Steam Generaters, Boiler and lntermediate Building, Design, Detailed Engineering, Manufacturing and Erection of 8 Boilers and Auxiliaries
  • Steam Turbo – Sets, Steam Turbine and Cooling Water Pumphouse Building, Erection of 4 Steam Turbines and Auxiliaries, Manufacturing and Erection of 4, 125 MVA 10,5 / 380 kV Step­ Up Transformers and Auxiliary Transformers, Partial Manufacturing and Complete Erection of Cooling Water System, Detailed Engineering and Construction of 135 m. high 120 m. base diameter 2 Natural Draft Dry Cooling Tower (concrete)
  • Water Treatment Plant (4x 25 m3/h.), Building, Design, detailed Engineering, Manufacturing and Erection and Commissioning of all facilities and equipment for Treatment of Cooling and Make-up Water
  • Central Control Building, Buildings, Complete Erection of all Switchgears and Control Panels and Desks
  • 380 kV / 154 kV Switchyard, Civil works and Steelstructure, Manufacture of Partial Equipment and Erection of the whole Switchyard, 380 kV Switchgear Building
  • lnfrastructure, Levelling of the Whole Area, Drainage Systems, Fire Fighting System, Cable Ducts including Cabling, Roads
  • Auxiliaries, HVAC systems, Raw Water Storage Basin, Fire Fighting Building, Oil Separator, Erection of Natural Gas Pipeline, Equipment Foundations

Key Quantities

Earthworks 1,250,000 m³
Concrete 80,000 m³
Formwork 200,000 m²
Reinforcing Steel 7,000 tons
Structural Steel 8,000 tons
Mech. Equipment 8,000 tons
Insulation & Paint 43,000 m²

Gallery