The Tunçbilek II Thermal Power Plant project completed in 1978 was the first power plant project that was undertaken by ENKA in its history. The project’s scope of work included civil, building works, steel structure fabrication and erection works of a 150 MW thermal power plant. The construction work mainly consisted of Boiler, Turbine and Bunker Buildings, water supply and treatment systems, stack and service buildings. The stack is 120 m high and constructed by sliding forms.
TUNÇBILEK II THERMAL POWER PLANT
Project Description
First Power Plant Project in history of ENKA
Key Quantities
Excavation | 500,000 m3 |
Piling (80 cm) | 10,000 m |
Formwork | 110,000 m2 |
Reinforcing steel | 3,500 t |
Concrete | 45,000 m3 |
Cladding | 60,000 m2 |
Steel Structure fabrication and erection | 2,500 t |