CLIENT

Turkish Electricity Authority – TEK

SCOPE OF WORK

Procurement, Construction

SECTOR

Power Plants

LOCATION

Tunçbilek, Türkiye

PROJECT DURATION

March 1973 – August 1978

Project Description

The Tunçbilek II Thermal Power Plant project completed in 1978 was the first power plant project that was undertaken by ENKA in its history. The project’s scope of work included civil, building works, steel structure fabrication and erection works of a 150 MW thermal power plant. The construction work mainly consisted of Boiler, Turbine and Bunker Buildings, water supply and treatment systems, stack and service buildings. The stack is 120 m high and constructed by sliding forms.

First Power Plant Project in history of ENKA

Key Quantities

Excavation 500,000 m3
Piling (80 cm) 10,000 m
Formwork 110,000 m2
Reinforcing steel 3,500 t
Concrete 45,000 m3
Cladding 60,000 m2
Steel Structure fabrication and erection 2,500 t

Gallery