The Produced Water 2 Facility project, on which we had started working in 2019, was 20% complete in December 2020. ENKA Design Center is responsible for the design and engineering works of the project we are undertaking on the EPC basis. The completion rate for engineering works was 60% by the end of 2020 including HAZOP and 30% of 3D Design and Model Review were completed successfully with the involvement of the employer.
By the end of December 2020 project has been under way for 396 working days and 125,000 person-hours have been expended without lost time incident (LTI).