ENKA, in partnership with Bechtel, has achieved remarkable progress in the Future Growth Project (FGP) at Tengiz Oil Field. As part of the project, the 3GP, designed to boost production capacity, has hit major milestones, including the completion of the entire base scope by December 2023 with an impressive 16.8 million person-hours worked incident-free. Noteworthy achievements include on-time completion of key construction milestones, such as the mechanical completion of boilers, HP/LP conversion, and ERT Building. The team also excelled in executing critical phases like Specialty Line Cleaning and Steam Blow, showcasing dedication and precision in their work. As they gear up for Steam Blow Phase-2 in February 2024, the commitment to safety and timely execution remains at the forefront. Thanks to the whole project team for their outstanding efforts!