ENKA is working hard on its Besmaya Project, located in Baghdad. As of the end of February 2016, majority of engineering and procurement activities for Simple Cycle scope of the Baghdad Electrical Power Station – Besmaya Project have been completed.
Accordingly, since the commencement of the Project; total of 38,000 m3 of concrete have been poured, 4,700 tons of structural steel and 1,500 tons of storage tank plates have been erected. Overall EPC progress is circa 58% by the end of February, 2016.
Currently, 300 non-manual and 1,700 manual labors are working actively for the Besmaya Project.