Within the scope of the West Med Port Project, which is under construction in Nador, Morocco, all diaphragm wall and barrette pile works at Zones 2, 3 and 4 were completed by ENKA’s subsidiary Kasktaş as of September 11, 2021.
On September 22, mobilization works at Zone 1 were completed, which is the last area within the scope of West Med Port to be connected to the motorway network and the railway line when completed, and execution of diaphragm wall was commenced in the area.
The remaining works within the project are planned to be completed by December 2021.