AFŞIN ELBISTAN B 1,440 MW THERMAL POWER PLANT

CLIENT

State owned electricity company – EUAŞ

CONTRACTOR

ENKA-MHI-Babcock-GTT Consortium

SECTOR

Power Plants

LOCATION

Kahramanmaraş, Türkiye

CONTRACT TYPE / SCOPE OF WORK

Lump Sum Turn Key / Detailed Engineering, Procurement, Construction

PROJECT DURATION

June 2000 – August 2007

Project Description

In August 1998, the state owned company for electricity generation – EUAŞ awarded the turn-key construction of a conventional-type coal-fired thermal power plant, with a nominal capacity of 1,440 MW to the consortium of  ENKA, Mitsubishi Heavy Industries Ltd. (MHI), Babcock Kraftwerkstechnik GmbH and Gama-Tekfen-Tokar JV (GTT).

ENKA-MHI-Babcock-GTT Consortium’s scope covered design, engineering, equipment supply, construction, commissioning and putting into operation of  Afşin Elbistan B 1,440 MW thermal power plant.

The project included the construction and installation of 4 steam turbojets, the flue gas desulphurization plant, the slag and ash handling system, the raw water supply system, the water treatment plant, the coal handling system, the cooling system, all ancillary plants, generating plants with their auxiliaries, storage facilities and the necessary workshops, operation and auxiliary buildings as well as all low, medium and high voltage switchgears, control and monitoring equipment and the power transformers. The complete implementation of design as well as tests, trial runs, acceptance tests and maintenance until the temporary acceptance date, the training of all operating personnel and the provision of all necessary consumables were also included in the project.

ENKA Scope of Services

ENKA’s scope included the construction of the turbine building, cooling towers, process buildings, 154-380 kV Switchyard, pipe and cable trenches; supply and construction of steel pipeline with a length of 2×33 km, high level tank and pump station; construction and erection of ash handling facilities; pipe racks; supply and erection of the cooling water pipes; erection of the turbine-generator units, auxiliary facilities; electro-mechanical erection of the whole supply units (Balance of Plant); erection of all the external process pipes.

Key Quantities

Steam Generators 4 x 360 MW
Stacks 2 x 150 m
Steel Structures 55,000 t
Boilers & Ducts (erection) 35,000 t
Refractory Works 8,500 t
Insulation Works 315,000 m2
Cladding 130,000 m2
Concrete 188,000 m³
Painting 1,150,000 m2
Equipment Erection 45,000 t